Pros and cons of river dredging
By LAWRENCE HAJNA
Courier-Post staff
Published: December 30. 2005
(from Jersey Coast Anglers
Association February 2006 Newsletter)
The following Q&A examines the history of the river dredging project and
summarizes the interests of the stakeholders.
Q: What is the proposal?
A: The river's
main shipping channel has been set at a depth of 40 feet (mean low water
depth) since World War II, when it was last deepened to accommodate
battleships being built in Philadelphia. In 1992, Congress first
authorized deepening the river's main shipping channel to 45 feet at the
request of the Delaware River Port Authority.
The DRPA's charter had just been changed from solely operating the bridges
and PATCO. The stated idea was to benefit the region's refineries by
allowing tankers to carry more oil up the river without unloading some at
the mouth of the bay, a process known as lightering. But port business
leaders saw the deepening as an opportunity to attract larger cargo ships
that need deeper water.
Q: Where would the river be dredged?
A: The project
boundaries are from the Beckett Street terminal in Camden to the mouth of
Delaware Bay, about 102 miles.
Q: How much would it cost?
A: Estimates have
fluctuated widely.
The U.S. Army
Corps of Engineers had been using a figure of $311 million, but in
September revised the figure to $264 million.
The federal
government would pay $161 million. DRPA and the states of New Jersey,
Delaware and Pennsylvania would have to contribute about $103 million.
There is no money budgeted by the federal government for the project.
Q: How much sediment would be removed?
A: The Army Corps
estimates the project will generate 26 million cubic yards of sediments --
about 18.7 million cubic yards from the river and 7.3 million cubic yards
from the bay.
Q: Where will they go?
A: This is the
biggest question swirling around the project.
Sediments dredged from the bay will be used to rebuild wetlands along the
bay in New Jersey and Delaware. The Army Corps has identified six existing
upland sites and three new sites along the river in Gloucester and Salem
counties to accept spoils, which could create hills up to 75 feet high.
Pennsylvania and
Army Corps officials have studied using spoils to fill in mines in
Northeastern Pennsylvania and stop the flow of acid-tainted water into
streams and rivers. Several years ago, the Army Corps estimated this would
add $190 million to the cost of the deepening project.
Q: Who is in favor of the project?
A: Longshoremen
and trade unions, the South Jersey Port Corp., Pennsylvania's House of
Representatives, Pennsylvania Gov. Ed Rendell and Pennsylvania's DRPA
commissioners.
Q: Who opposes the project?
A: Most South
Jersey state lawmakers, U.S. Rep. Rob Andrews, South Jersey's DRPA
commissioners, and environmental groups, including the Delaware
Riverkeeper Network.
Q: Why do supporters say the project must be done?
A: Shipping and
labor unions argue the Port of Philadelphia is at a significant
disadvantage for cargo shipping, arguing bigger cargo ships are now using
ports at New York and Norfolk, Va., which have deeper shipping channels.
Q: Why do opponents say the project is not necessary?
A: They say Philadelphia, unlike New York and Norfolk, is too far upriver
to attract bigger ships. They say new berths are needed in places like
Paulsboro and Salem to accommodate more of the same size ships that now
use the river.
Opponents also
say that many of the larger ships today need 50-foot channels and that the
river cannot be deepened this much because bedrock lies just below the
sediment.
Q: What are the environmental impacts of dredging?
A:
Environmentalists contend the project will disturb habitat for species
such as the short-nose sturgeon, blue crabs and horseshoe crabs.
They fear that
digging into sediments that have lain dormant for decades would release
harmful industrial contaminants, although the Army Corps insists most of
the sediments are clean and even virgin material.
Opponents also contend that digging into the river could crack a massive
underground water supply known as the Potomac-Raritan-Magothy aquifer,
potentially contaminating it.
Q: Would the project generate new jobs?
A: While DRPA has
conducted a study showing the ports of Camden and Philadelphia generate
some 75,000 jobs directly and indirectly, no one has performed a detailed
study of the impact a deeper river would have economically or whether it
would indeed attract newer and bigger ships.
Federal law required the Army Corps to conduct a cost-benefit analysis to
ensure taxpayers don't lose money if the project is built.
The Corps has looked primarily at impacts to refineries but also factored
in effects on the shipment of some products such as scrap iron and cement
slag.
Triggered by
environmental concerns, South Jersey officials demanded an independent
audit of the project's anticipated economic benefits. The federal General
Accountability Office found that the project would lose about 50 cents for
every dollar spent on construction, in contrast to initial Army Corps
calculations that estimated the project would generate $1.40 for every
dollar spent.
The Army Corps conducted a new analysis, showing the project would
generate $1.15 in economic benefit for every dollar spent.
Q: Why is the project on hold?
A: The state of
Delaware has withheld a permit the Army needs to disturb the river bottom.
New Jersey also says the Army Corps needs to update studies on
environmental impacts disposal sites would have.
New Jersey also
has not taken action to appropriate its share of project funding.
Because of these
issues and the economic questions, DRPA has not signed a project
cooperation agreement with the Army Corps.
[News Contents]
[Top]
